Current checkpoint (2026-11-18)

  • All ten planned weeks are ticketed. Weeks 1-6 are closed; outstanding core acceptance spans Weeks 7-10. Week 7/8 integration and shared measurements remain prerequisites, followed by the Week 9 rehearsal/writeups and Week 10 final presentation.
  • Bound pack-index caching and verify replacement detection #71/Document storage formats and add a reproducible snapshot demo #72 deliver the latest storage changes, evidence, and draft writeup. Modules 2-4 writeups, the full demo, shared project/network benchmark, teammate reproduction, and presentation evidence remain open through their existing tickets.
  • Include Week 9 - Team: Track the project with mini-git + recovery rehearsal #73's project-source trial in the final runbook and evidence. Close prerequisite tickets only after their remaining criteria are demonstrated; merging partial contributions alone does not close the project.
  • Planning assumption: four owners work in parallel, with completed module owners helping M4. Roughly four team working weeks remain on the critical path; this is an estimate, not a dated commitment. There is no required Week 11 or new stretch phase.

Scope

Finish the final week of the planned Weeks 9-10 buffer. Earlier open issues remain prerequisites, not assumed accomplishments. Fix reproducible blockers, finalize the writeup, and verify the delivered behavior at the team's recorded demo revision. Preserve existing module contracts; optional stretch work is only included if separately selected and completed after core readiness.

Steps

  1. Reconcile the Week 9 checkpoint and stretch triage in Week 9 - M4: Integrated demo rehearsal + stretch-goal triage #63 with all four owners. Track unfinished Week 7 - M4: Network diagnostics + end-to-end performance baseline #47/Week 8 - M4: Network performance + final end-to-end checkpoint #58 benchmarks and integration work explicitly. Every remaining blocker needs a reproduction, owner, and fix/defer rationale; optional stretch goals do not replace core acceptance.
  2. Assemble the final runbook in docs/demo.md: clean install/build, supported Python version, disposable repositories/token, terminal roles, commands, expected results, server start/stop, reset/cleanup, and a recorded revision. Link it and all four finalized module writeups from README or the handoff index.
  3. Have a teammate run the complete walkthrough at that revision using separate CLI processes: init -> add -> commit -> branch -> checkout -> fast-forward -> clean two-parent merge -> push -> pull. Include two branches with shared objects, nested paths, executable modes, binary data, and packed-only/mixed storage; verify tips, reachable history, bytes/modes, index, status/diff/log.
  4. Verify recovery: repeated sync transfers zero object payloads, stale/diverged pushes are refused, pull conflict -> resolve -> add -> two-parent commit works, and interrupted transfer -> retry succeeds. Failed transfers preserve refs/HEAD/index/files while verified objects may remain; intentional conflicts retain markers/state. Ensure the next client can connect after a bad session.
  5. Finish Week 7 - M4: Network diagnostics + end-to-end performance baseline #47/Week 8 - M4: Network performance + final end-to-end checkpoint #58's shared benchmark or record its incomplete status as an explicit handoff limitation. Consolidate all module measurements with revision IDs, environment, fixtures, commands, timings, stored bytes, and payload counts. Do not equate the M1 blob fixture or M2 file fixture with a completed end-to-end network baseline.
  6. Finalize the Module 4 writeup: framing/authentication, missing-object transfer, both-parent traversal, ref publication, push rejection, pull integration, retry behavior, tradeoffs, and lessons learned. Document plaintext TCP/token limitations and any shipped transfer-size limit; keep credentials out of captures.
  7. Run scripts/build.sh and scripts/quality-check.sh on the final integrated revision. Keep large benchmarks opt-in and automated network tests on loopback/port 0 with bounded waits and cleanup. Record a teammate reproduction and deliver the live or recorded presentation with a revision/link and fallback runbook.
  8. Link the final evidence, writeups, known limitations, and owned follow-ups. Close prerequisite issues only when their acceptance criteria are verified. Open a linked PR and request teammate review; no release publication or new stretch feature is required by this ticket.

Done when

  • Clean setup/build and full local/network demo reproduced by a teammate at a recorded revision
  • Recovery guarantees and final quality checks pass
  • All four writeups, performance evidence, demo instructions, and presentation evidence are linked
  • Unfinished prerequisites and remaining limitations have explicit owners and dispositions

Activity

  1. added
    module-4
    week-10
    on Nov 8, 2026
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment