Offline Multilingual Project Planning Engine

Resources

Stars

1 star

Watchers

0 watching

Forks

Repository files navigation

SyntaxMesh

Offline project planning with a descriptive language.

SyntaxMesh is an independent implementation of the TaskJuggler planning model: a scheduling engine that reads plain-text project files (.tjp), resolves dependencies, allocates resources, computes dates and costs, and generates reports — HTML tables, Gantt charts, CSV/JSON, MSPDI, iCalendar and more. The engine is written in TypeScript, developed and run on Deno, and needs no application server.

Status of work: the real scope, progress and execution order live in docs/syntaxmesh/fases/plano.md (canonical 21-phase plan + complementary phases 22–24) and in CURRENT.md. Architectural decisions are in docs/syntaxmesh/decisoes/ (ADRs). This README is a general overview and defers to those files in case of conflict. The original Portuguese base-specification is preserved in docs/syntaxmesh/01-visao.md.

Everything described below is already implemented and covered by the engine's test suite (phases 1–18 of the plan are complete). Each capability has a short syntax example — all of them are real, parseable TaskJuggler/SyntaxMesh code.


Projects, tasks and milestones

A project file opens with a header (ID, name, version and timeframe) and a tree of tasks. Tasks carry effort or an explicit duration, and can be pinned with dates or marked as zero-duration milestones. The scheduler turns all of this into a concrete timeline.

project office "Office Building" "1.0" 2025-01-06 - 2025-06-30 {
  timezone "UTC"
  timeformat "%Y-%m-%d"
  now 2025-02-01
}

task build "Construction" {
  task foundation "Foundation" { effort 10d }
  task structure  "Structure"  { effort 20d }
  task handover   "Handover" {
    milestone                     # zero-duration checkpoint
    start 2025-06-15
  }
}

Task dependencies

Tasks link with depends (successor) and precedes (predecessor). References use scope prefixes (!task within the parent, !!container.task from a wider scope), accept several at once, and support a working-time gap (gaplength) or calendar-time gap (gapduration) — the basis of finish-to-start, start-to-start and other dependency types.

task finishing "Finishing" {
  task wiring "Electrical" { effort 5d }
  task plumbing "Plumbing" { effort 4d }
  task plaster "Plastering" {
    effort 6d
    depends !wiring, !plumbing          # both must finish first
  }
  task paint "Painting" {
    effort 3d
    depends !plaster { gapduration 2d } # starts 2 days after plastering
  }
}

Resources, calendars and availability

Resources form a tree (groups and people) with hourly/period rates that are inherited down the tree. Working weeks, holidays and per-resource leaves constrain when work can actually happen, so the schedule respects real availability.

leaves holiday "New Year" 2025-01-01

resource crew "Crew" {
  rate 40.0
  resource alice "Alice" {
    rate 55.0
    leaves annual 2025-07-01 - 2025-07-10   # Alice is away
  }
  resource bob "Bob" { }
}

task shell "Erect shell" {
  effort 8d
  allocate alice, bob        # both work on it, splitting the effort
  responsible alice          # accountable, without consuming effort
}

Materials

Materials have a unit, a unit price and an account that aggregates their cost. A task consumes stock by referencing the material and a quantity. Stock movements (± ) are booked directly against the inventory.

account matcost "Materials" { aggregate materials }

material steel "Steel" {
  unit "kg"
  unitprice 2.5
  chargeset matcost 100%
}

task slab "Foundation slab" {
  effort 3d
  material steel 500        # consumes 500 kg of steel
}

Composite materials

A material can be defined as a recipe of other materials. Its unit price is then computed from the components (component × quantity, recursively), so you price an assembly from its parts instead of hard-coding a number. A composed material must not declare its own unitprice.

material cement "Cement" { unit "kg"  unitprice 0.2 }
material gravel "Gravel" { unit "kg"  unitprice 0.1 }

material concrete "Ready-mix Concrete" {
  unit "m^3"
  material cement 350       # 350 kg of cement per m^3
  material gravel 1800      # per-m^3 price = 350×0.2 + 1800×0.1
}

Accounts, costs and revenues

The accounting model mirrors a chart of accounts: cost and revenue accounts form a tree, balance defines how they roll up, and tasks charge amounts to a chargeset — either a flat value (at start/end) or a rate distributed over time. This gives cost, revenue, profit and cash-flow at any point of the plan.

project house "House Build" "1.0" 2025-03-01 - 2025-09-30 {
  currency "USD"
}

account cost "Project Cost" {
  account labor "Labor"
}
account rev "Payments"
balance cost rev

task dig "Excavation" {
  effort 4d
  chargeset labor 100%              # 100% of cost to the Labor account
  charge 170 perday                 # running cost spread over the task duration
}

task deposit "Client deposit" {
  milestone
  chargeset rev
  charge 21000.0 onstart        # revenue recognized at the milestone
}

Reports and Gantt charts

Reports are declared in the same file and rendered as self-contained output. Columns cover everything the engine computes (dates, effort, cost, custom attributes, …), the chart column emits an HTML/CSS Gantt with dependency arrows and milestones, and the same model exports to CSV, JSON, Markdown, MSPDI XML (MS Project), iCalendar and TJP round-trip.

taskreport "Plan" {
  formats html
  headline "Schedule and Gantt"
  columns bsi { title 'WBS' }, name, start, end, effort, cost, chart
}

accountreport "Financials" {
  formats csv
  columns name, cost, revenue, balance
}

Tracking progress: schedule and cost

Set now to the reporting date and record what actually happened — complete percentages, bookings of real work, and journalentry notes. The engine replans around the actuals and exposes the delta (done/left effort, status, cost variance) so you track slippage and budget against the plan.

project track "Rollout" "1.0" 2025-10-01 - 2025-10-31 {
  now 2025-10-15
}

resource dev "Developer" { rate 400.0 }

task impl "Implementation" {
  effort 10d
  allocate dev
  complete 40                                  # 40% done as of `now`
  journalentry 2025-10-10 "Started implementation phase"
}

taskreport "Status" {
  formats html
  columns name, start, end, effort, effortdone, effortleft, complete, status, chart
}

Scenarios and what-if

Define scenarios (optionally nested) and override any attribute per scenario — effort, dates, costs, custom fields — without duplicating the plan. Reports can show one scenario or line up several side by side to compare a baseline against optimistic/pessimistic outcomes.

project risky "Plan vs. Reality" "1.0" 2025-12-01 - 2025-12-31 {
  scenario baseline "Original Plan" {
    scenario delayed "Pessimistic" {
    }
  }
}

task design "Design" {
  effort 5d
  delayed:effort 8d              # only the `delayed` scenario is slower
}

taskreport "Comparison" {
  formats html
  headline "Baseline vs. Pessimistic"
  scenarios baseline, delayed
  columns name, start, end, effort, chart
}

Multilingual syntax

Files can be written in English, Portuguese (pt-BR) or Spanish — different words, same semantics. The parser normalizes every keyword to one canonical representation, so equivalent files produce identical plans. More languages can be added without touching the engine.

language "pt-BR"

projeto obra "Minha Obra" "1.0" 2025-01-06 - 2025-06-30

tarefa fundacao "Fundação" {
  esforço 10d
}
tarefa estrutura "Estrutura" {
  depende !fundacao
  esforço 15d
}

Extensible language

extend adds your own typed attributes (text, number, date, reference, richtext, markdown) to any object, with inherit and scenariospecific options — then set them like built-in ones and surface them as report columns.

project ext "Site Inspection" "1.0" 2025-05-01 - 2025-05-31 {
  extend task {
    text Inspector "Inspector"
    number Score "Score"
  }
}

task audit "Audit" {
  effort 2d
  Inspector "A. Rivera"
  Score 8.5
}

Delivery roadmap

The engine is the product; the interfaces ship in three waves:

  1. Command-line interface (next — phase 24) A tj3-equivalent multi-runtime CLI (Deno / Bun / Node) that processes .tjp files, runs the scheduler and writes reports to disk. It will also be the harness for the compatibility test wave against real TaskJuggler.

  2. VS Code extension (phase 22) Language support for .tjp: syntax highlighting, grammar, keyword documentation and an LSP server built on the same canonical engine.

  3. Offline web app (PWA) (phases 19–20, last) Browser edition with local storage (IndexedDB + OPFS), service worker, and a Preact + Signals + BeerCSS UI — installable, fully offline, static hosting only.

The canonical execution order is 16 → 17 → 18 → 23 → 24 → 21 (wave 1) → 22 → 21 (wave 2) → 19 → 20 → 21 (wave 3). Phases 1–18 (the entire engine) are complete; the remaining phases package it into the deliverables above, starting with templates (23) and the CLI (24). See CURRENT.md for live status.


Technology

  • Deno only — no Node.js, no npm/yarn/pnpm, no node_modules. Dependencies are managed in deno.jsonc via npm:/jsr: specifiers.
  • TypeScript in strict mode for the engine (packages/core), runtime-agnostic: the core never touches DOM, Preact, IndexedDB or the UI.
  • Preact + Signals + BeerCSS for the (future) web UI; Material Symbols for icons.
  • TaskJuggler as reference, not as a dependency: the Ruby sources under docs/taskjuggler/lib/taskjuggler/ are the behavioral ground truth for ports, and the real tj3 binary plus golden snapshots validate schedules, reports and the Gantt chart.
  • Tests use @std/testing/bdd + @std/assert.

Development

Requirements: Deno 2.x and (optionally) TaskJuggler (tj3 + Ruby) to regenerate golden tests.

deno task test        # unit + integration tests
deno task tests       # full quality gate: type check, lint, fmt, doc lint, tests
deno task check:all   # type check per package
deno task lint        # linter
deno task fmt         # formatter
deno task dev         # dev server on port 3000 (early PWA shell)

Every feature ships TDD-first, one atomic task at a time, with golden tests against the real tj3 — see docs/syntaxmesh/09-regras-para-ia.md for the working rules.

Documentation map

Where What
CURRENT.md Current status and next step (start here)
docs/syntaxmesh/fases/plano.md Canonical 21+3 phase plan
docs/syntaxmesh/decisoes/ Architecture decision records
docs/syntaxmesh/01-visao.md Original base specification (pt-BR)
docs/Learning/ Worked examples mwe001–mwe009

License

GPL-2.0-only — see LICENSE.

About

Offline Multilingual Project Planning Engine

Resources

Stars

1 star

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages